Δευτέρα , 11 Μάιος 2026
Home ΝΑΥΤΙΛΙΑ NL 342/25 |  Compliance Update: 2025 Emissions Reporting & Verification Deadlines
ΝΑΥΤΙΛΙΑ

NL 342/25 |  Compliance Update: 2025 Emissions Reporting & Verification Deadlines

Refers to: Ship-owners, Operators, Masters and Managers of PHRS certified vessels

Effective Dates: N/A

As the reporting cycle for 2025 emissions approaches, it is essential for all operators to prepare for the upcoming verification milestones. To support timely compliance and ensure that PHRS can complete verification activities without delay, please review the key actions and deadlines outlined below.

This update covers requirements under:

 

FuelEU Maritime (FuelEU)

EU Monitoring, Reporting and Verification (EU MRV)

EU Emissions Trading System (EU ETS)

IMO Data Collection System (DCS) & Carbon Intensity Indicator (CII)

Key Submission Deadlines

 

FuelEU

31 January 2026 – Submission of the ship-specific FuelEU report to the accredited verifier.

31 March 2026 – Completion of verification.

30 April 2026 – Verified FuelEU data must be confirmed in THETIS, including any applicable flexibility mechanism records.

Refer to the FuelEU Timetable for a complete overview of compliance milestones, including issuance of the Document of Compliance and payment of any penalties.

 

EU MRV

31 March 2026 – Ship-level and company-level emissions data must be submitted to THETIS and verified.

Note: Some Administering Authorities may request verified data earlier, but not before 28 February 2026.

EU ETS

31 March 2026 – Verified company emissions data (as reported in THETIS under EU MRV) must be entered into the Union Registry via the Maritime Operator Holding Account (MOHA) and validated by the Administering Authority.

If data is not submitted by 1 April 2026, the MOHA will be blocked.

If a company no longer falls within EU ETS scope (e.g., no EU/EEA port calls in the reporting year), it may request that its MOHA be designated as “excluded.”

 

IMO DCS & CII

31 March 2026 – Submission of annual emissions data.

31 May 2026 – Verification completed and Statement of Compliance issued on behalf of the Administration.

30 June 2026 – Verified data submitted to the IMO GISIS system by the verifier.

PHOENIX REGISTER OF SHIPPING

UPOLDING QUALITY, ENSURING COMPLIANCE

 

Related Articles

Katradis Marine Ropes Industry SA High-Quality Anchors & Chains, Holiding power you can rely on

#Anchoring is one of the most critical operations a vessel performs. The...

Why Trump Ended “Project Freedom” in Hormuz

Yesterday, US President Donald Trump announced that the US operation “Project Freedom”...

The Economic Value of European Shipping: Key for Europe’s Security with 34.5% of Global Fleet

Ahead of an event at the European Parliament on the strategic role...

MacGregor to supply deck machinery for ultra-large cable-laying vessels

MacGregor has been selected to supply a comprehensive package of offshore and...